News

Timeline:

September 16, 2022- Gas Processing Facility Land Lease: Final finding reapproved by DNR.


March 07, 2021 - "SES Midstream appeals division’s decision on Deadhorse lease to DNR commissioner; Ray Latchem says project is shovel ready. " 


Link: https://www.petroleumnews.com/pntruncate/886228338.shtml


September 2020- COE Gravel Permit Approved. 


August 19, 2020- Without notice, the final finding is rescinded. 


July 2020- Prudhoe Bay land lease secured.


Link: https://aws.state.ak.us/OnlinePublicNotices/Notices/View.aspx?id=198480


June 08, 2020- Gas Processing Facility Land Lease: Final finding approved by DNR.


June 2020 - Deadhorse Gas Treatment Project proposed.


Link: https://www.petroleumnews.com/pntruncate/311790897.shtml